The New York Independent System Operator is projecting its first ever statewide power grid shortfall coming as early as 2033.

The ISO's 2026 Reliability Needs Assessment is projecting the state's electricity supply projected to be insufficient to reliably meet demand, with the shortfall at 225 megawatts in 2033 and growing to more than 1,850 megawatts by 2036. Power shortfalls have been projected in past Independent System Operator reports, but those reliability shortfalls have largely centered downstate.

Those downstate reliability needs are still included in the most recent report as well. The Reliability Needs Assessment, which is released every two years, identified reliability needs in New York City and the Lower Hudson Valley. New York City is projected to be deficient by 400 megawatts in 2032, growing to 1,850 megawatts by 2036. The Lower Hudson Valley deficiency grows from 130 megawatts in 2032 to 1,950 megawatts in 2036.

The reliability issues projected in the 2024 Reliability Needs Assessment have grown over the past two years. In 2024, the assessment warned that statewide resource margins were steadily declining, leaving virtually no surplus power by 2034 without new generation, transmission upgrades, or demand-response additions. It also showed a specific reliability shortfall in New York City starting at 17 megawatts in summer 2033 and growing to 97 megawatts in summer 2034.

The reasons behind power shortfalls have also changed. Two years ago, the ISO attributed narrowing reliability margins to growing peak power demand from building and transportation electrification, large commercial projects and the scheduled deactivation of 517 megawatts of small natural gas plants owned by the New York Power Authority.

The release of the 2026 Reliability Needs Assessment comes the same day Gov. Kathy Hochul released the Master Plan for Responsible Advanced Nuclear Development in New York. The plan is a statewide roadmap to achieve Hochul's Nuclear Reliability Backbone to create five gigawatts of new nuclear power. Dunkirk has thrown its hat in the ring to possibly be the site of a nuclear power plant at the former NRG power plant. It was one of eight communities to express an interest in the opportunity in 2025.

"Expanding emission-free, round-the-clock nuclear power is a cornerstone of my all-of-the-above approach to ensure we have enough energy to keep the lights on and costs down for New Yorkers," Hochul said. "The completed Advanced Nuclear Master Plan can serve as a national model by pairing our ambitious target of five gigawatts of new nuclear generation with a comprehensive strategy to support thoughtful development and deployment of what will be the largest buildout the country has seen in more than three decades."

Independent System Operator officials are also calling on an all-of-the-above approach to power generation to resolve the identified reliability needs. While transmission investments can help address local reliability needs in New York City and the Lower Hudson Valley, they cannot resolve the statewide resource shortfall, ISO officials said. A combination of new generation, repowered resources, energy storage, dependable demand reductions, flexible large loads, and additional transmission will be required to maintain reliability over the next decade.

"New York's reliability needs are no longer a distant concern," said Zach Smith, Senior Vice President of System & Resource Planning. "Electricity demand is growing as the availability of reliable power is increasingly uncertain. New generation and transmission resources take years to plan, permit, and build, so the reliability needs identified in this report must be addressed today."

Several trends are contributing to these forecasted deficiencies, including growing electricity demand and reductions in available power from both in-state resources and neighboring regions. A major source of future demand growth is approximately 2,700 megawatts of forecasted large loads, including about 1,000 megawatts from manufacturing facilities and 1,700 MW megawatts from data centers.

The age and availability of New York's generation fleet is also a growing reliability concern, according to the ISO report. The report found that 4,600 megawatts of fossil generation will be more than 70 years old by 2036, increasing the risk of outages, equipment failures and retirements. The Reliability Needs Assessment accounts for that risk by projecting 2,600 megawatts of generation to be unavailable by 2036.

The ISO will update the findings of the RNA to reflect eligible changes in generation and transmission projects, demand forecasts, and other system developments that could reduce or eliminate the identified reliability needs. If needs remain, the ISO will solicit and evaluate market-based and regulated solutions through development of the 2027-2036 Comprehensive Reliability Plan.